Crusoe, a Denver-based data center developer, confirmed Friday that it has sold an unfinished data center project in southeastern Wyoming to Google. Crusoe is valued at $30.9 billion, according to the source.

Google had tried and failed to become a customer for the project. The report says Google is taking over development after reportedly raising concerns about its cost and construction timeline under Crusoe's management.

Crusoe first announced the project last year with Tallgrass, a Blackstone-backed infrastructure company. The plan called for eventually scaling the site to 10 gigawatts of power capacity.

Google did not disclose what it paid. It has announced plans to invest $17 billion to develop the campus.

The report says the deal shows how hard it can be for independent developers to deliver large projects on time and on budget, given challenges in securing equipment and power. It also says local opposition can complicate development. Bloomberg first reported the sale in June.

Google is still working with Crusoe. Crusoe is developing another data center for Google near Amarillo, Texas.